Stonehaven Transit identifies that 80% of light rail delays are due to 'Sensor Misalignment.' A control chart of the alignment process shows that while all measurements are within the ± 3σ control limits, the last seven points have all been above the mean.
What does this 'Rule of Seven' tell the project manager?
- The project manager must immediately halt all rail operations.
- The specification limits are too tight for this process.
- The process is in control because no points are outside the limits.
- The process is out of statistical control due to an assignable cause.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?