During a status meeting for Trestle Ports, a stakeholder claims they never received the previous month's performance report. The project manager confirms the email was sent two weeks ago.

What does this situation illustrate regarding the sender's responsibility?

  1. The receiver is at fault for not checking their inbox or acknowledging receipt, before confirming the relevant stakeholders agree.
  2. The communication management plan should be immediately audited by the PMO.
  3. The sender is only responsible for the successful transmission of the data.
  4. The sender is responsible for ensuring the message was clear, received, and understood.