easy · Project Management Professional predictive
During a status meeting for Trestle Ports, a stakeholder claims they never received the previous month's performance report. The project manager confirms the email was sent two weeks ago.
What does this situation illustrate regarding the sender's responsibility?
- The receiver is at fault for not checking their inbox or acknowledging receipt, before confirming the relevant stakeholders agree.
- The communication management plan should be immediately audited by the PMO.
- The sender is only responsible for the successful transmission of the data.
- The sender is responsible for ensuring the message was clear, received, and understood.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?