easy · Project Management Professional Predictive (Plan-Driven)
During a status meeting for Trestle Ports, a stakeholder claims they never received the previous month's performance report. The project manager confirms the email was sent two weeks ago.
What does this situation illustrate regarding the sender's responsibility?
- The receiver is at fault for not checking their inbox or acknowledging receipt, before confirming the relevant stakeholders agree.
- The communication management plan should be immediately audited by the PMO.
- The sender is only responsible for the successful transmission of the data.
- The sender is responsible for ensuring the message was clear, received, and understood.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards