Grayling Software is behind schedule. The project manager wants to remove several non-critical features to meet the deadline.

What is required?

  1. A simple update to the WBS to remove the activities.
  2. Approval from the lead developer to ensure the software still functions.
  3. No formal action is required if the client hasn't paid for those features yet.
  4. A formal change request to modify the scope and schedule baselines.