hard · Project Management Professional predictive
Plover Software is using a Kanban board for maintenance tasks. There are currently 12 items in the 'In Progress' column, and the team completes an average of 3 items per week.
What is the average cycle time for a task?
- 9 weeks
- 0.25 weeks
- 36 weeks
- 4 weeks