medium · Project Management Professional predictive
A project at Fenwick Grid is building a new solar farm. A local environmental group requests that the fence height be lowered. The PM believes this will increase the risk of theft.
What is the best action for the PM to take?
- Ask the environmental group to pay for the additional security guards that theft would necessitate.
- Immediately lower the fence to maintain a good relationship with the local community.
- Decline the request to protect the project from the risk of theft.
- Log the change request and assess the impact on both the schedule and the risk register.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?