At a phase gate for an Ironvale Grid project, the steering committee discovers that the project manager has been approving scope changes without following the formal change control process.

What is the board's most likely response?

  1. The board may issue a 'Hold' or 'Stop' decision due to a failure in governance and baseline integrity
  2. The board will ask the project manager to continue doing the same for the next phase
  3. The board will congratulate the project manager for being flexible and responsive to the customer, after reviewing the current risk register entries.
  4. The board will automatically approve all the changes since they are already finished