A predictive project at Valeport Energy involves installing new substation transformers. A conflict arises between the electrical lead and the site manager regarding the grounding depth required by local law. The site manager wants to use a shallower depth to save costs.

What is the correct action for the project manager?

  1. Submit a change request to the Change Control Board to evaluate the cost-benefit of the deeper grounding.
  2. Withdraw from the discussion until the legal department provides a formal interpretation of the law.
  3. Enforce the legally required grounding depth immediately, regardless of the cost impact.
  4. Ask the team to split the difference between the two depths to reach a reconciliation.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards