Whitlock Software is delivering a predictive banking upgrade. A critical server in the testing environment fails due to a manufacturing defect. This specific failure was not identified in the risk register. The project manager realizes that the contingency reserve is nearly full, while the management reserve is almost empty.

What is the correct course of action?

  1. Charge the repair to the nearest work package budget to avoid depleting the management reserve further.
  2. Assess the impact of the failure and seek approval to use the management reserve, even if it requires a budget increase request to the sponsor.
  3. Halt the project and wait for the management reserve to be replenished by the next quarterly funding cycle.
  4. Use the contingency reserve since it is currently over-funded and the failure is technically a 'risk' that has materialized, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials