medium · Project Management Professional predictive
Whitlock Software is delivering a predictive banking upgrade. A critical server in the testing environment fails due to a manufacturing defect. This specific failure was not identified in the risk register. The project manager realizes that the contingency reserve is nearly full, while the management reserve is almost empty.
What is the correct course of action?
- Charge the repair to the nearest work package budget to avoid depleting the management reserve further.
- Assess the impact of the failure and seek approval to use the management reserve, even if it requires a budget increase request to the sponsor.
- Halt the project and wait for the management reserve to be replenished by the next quarterly funding cycle.
- Use the contingency reserve since it is currently over-funded and the failure is technically a 'risk' that has materialized, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?