Larkspur Health is procuring a modular clinic build through a Firm Fixed Price contract. During execution, the vendor suggests a higher-grade HVAC system that was not in the original SOW but would reduce long-term maintenance costs.

What is the correct response according to the PMP mindset?

  1. Analyze the total life-cycle cost impact and submit a change request if the benefit is justified.
  2. Reject the suggestion because the contract is FFP and scope is fixed.
  3. Ask the vendor to wait until the project is closed and handle it as operational maintenance.
  4. Accept the higher-grade system if the vendor provides it at no additional cost to the project.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials