hard · Project Management Professional Predictive (Plan-Driven)
Larkspur Health is procuring a modular clinic build through a Firm Fixed Price contract. During execution, the vendor suggests a higher-grade HVAC system that was not in the original SOW but would reduce long-term maintenance costs.
What is the correct response according to the PMP mindset?
- Analyze the total life-cycle cost impact and submit a change request if the benefit is justified.
- Reject the suggestion because the contract is FFP and scope is fixed.
- Ask the vendor to wait until the project is closed and handle it as operational maintenance.
- Accept the higher-grade system if the vendor provides it at no additional cost to the project.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards