medium · Project Management Professional predictive

At Dovetail Clinics, a project is following a predictive approach to renovate a surgery center. A surgeon requests a different type of overhead LED light. The project manager identifies this as a change.

What is the correct sequence of actions?

  1. Document in change log rightarrow Impact analysis rightarrow CCB disposition rightarrow Update baseline.
  2. CCB approval rightarrow Document in change log rightarrow Impact analysis rightarrow Update baseline.
  3. Impact analysis rightarrow CCB approval rightarrow Document in change log rightarrow Update baseline.
  4. Document in change log rightarrow Update baseline rightarrow Impact analysis rightarrow CCB approval.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials