hard · Project Management Professional predictive
Amberline Transit is managing a predictive signaling upgrade. The project has a Budget at Completion (BAC) of 1,200,000. At the current status date, the project is40%complete by budget, but the actual costs (AC) incurred are600,000.
What is the Cost Performance Index (CPI) for this project?
- 0.80
- 0.40
- 1.25
- 0.50
Sign up free to see the explanation and track your rank →