The project manager at Solstice Labs calculates an Earned Value (EV) of $45,000, a Planned Value (PV) of $50,000, and an Actual Cost (AC) of $48,000.

What is the current Cost Performance Index (CPI)?

  1. 0.9375
  2. 1.06
  3. -$3,000
  4. 0.90

Sign up free to see the explanation and track your rank →