medium · Project Management Professional predictive
The project manager at Solstice Labs calculates an Earned Value (EV) of $45,000, a Planned Value (PV) of $50,000, and an Actual Cost (AC) of $48,000.
What is the current Cost Performance Index (CPI)?
- 0.9375
- 1.06
- -$3,000
- 0.90
Sign up free to see the explanation and track your rank →