medium · Project Management Professional predictive
Hartmere Ports has a project with a BAC of $2,000,000. At the status date, EV is $900,000 and AC is $1,000,000. An unexpected permit delay occurred that cost $100,000, but it was a unique event that will not happen again.
What is the EAC using the atypical variance formula?
- $1,900,000
- $2,100,000
- $2,000,000
- $2,222,222
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?