medium · Project Management Professional predictive
Hartmere Ports is managing a dredging project using the twelve-second triage protocol. A risk that was previously identified as having low probability has just occurred.
What is the first thing the project manager should do?
- Submit a change request to increase the contingency reserve.
- Implement the planned risk response from the risk register.
- Perform a root cause analysis to see why the risk occurred.
- Notify the project sponsor about the risk event.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?