KomFi. Academy

medium · Project Management Professional Predictive (Plan-Driven)

During the execution of a Valeport Energy project, a critical path activity is crashed. The project manager uses 'Management Reserve' to pay for the additional resources.

What is the impact on the Cost Baseline?

  1. The Cost Baseline remains the same, but the total project budget increases.
  2. The Cost Baseline increases by the amount of the management reserve used.
  3. The Cost Baseline decreases to offset the increased spending efficiency.
  4. There is no impact, as crashing is an internal process within the baseline.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards