medium · Project Management Professional predictive
During the execution of a Valeport Energy project, a critical path activity is crashed. The project manager uses 'Management Reserve' to pay for the additional resources.
What is the impact on the Cost Baseline?
- The Cost Baseline remains the same, but the total project budget increases.
- The Cost Baseline increases by the amount of the management reserve used.
- The Cost Baseline decreases to offset the increased spending efficiency.
- There is no impact, as crashing is an internal process within the baseline.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?