medium · Project Management Professional predictive

Stonehaven Transit is expanding its project team from a core of 8 members by adding 4 new key stakeholders. The project manager needs to determine the impact on project coordination.

What is the increase in potential communication channels, and what is the required first action?

  1. The project adds 4 potential channels; the project manager should update the stakeholder engagement assessment matrix.
  2. The project adds 38 potential channels; the project manager should update the communications management plan to refine the sub-team structure.
  3. The project adds 38 potential channels; the project manager should escalate to the sponsor to request a dedicated communications lead, after reviewing the current risk register entries.
  4. The project adds 55 potential channels; the project manager should implement a mandatory daily status meeting for all 12 members.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials