medium · Project Management Professional predictive
Stonehaven Transit is expanding its project team from a core of 8 members by adding 4 new key stakeholders. The project manager needs to determine the impact on project coordination.
What is the increase in potential communication channels, and what is the required first action?
- The project adds 4 potential channels; the project manager should update the stakeholder engagement assessment matrix.
- The project adds 38 potential channels; the project manager should update the communications management plan to refine the sub-team structure.
- The project adds 38 potential channels; the project manager should escalate to the sponsor to request a dedicated communications lead, after reviewing the current risk register entries.
- The project adds 55 potential channels; the project manager should implement a mandatory daily status meeting for all 12 members.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?