hard · Project Management Professional Predictive (Plan-Driven)

Westfork Municipal is closing a infrastructure project. The project manager is overwhelmed with administrative tasks and decides to delegate the 'Final Report' to a junior team member who joined the project in its final month.

What is the main risk in this decision?

  1. The junior team member might not know how to use the organizational templates correctly, leading to a compliance breach, before confirming the relevant stakeholders agree.
  2. The junior team member may take too long to complete the report, delaying the project's financial closure.
  3. The team may feel that the project manager is disengaging too early, leading to a drop in final-month morale.
  4. The report may lack the depth of contextual understanding required to accurately capture root causes and complex stakeholder dynamics.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards