medium · Project Management Professional predictive

CASE PEAKSTONE RAIL: STATION MODERNIZATION The station modernization project's cash flow S-curve shows that in month 6, the cumulative planned spend is 350,000, while the organizational funding limit for that period is320,000.

What is the most appropriate action for the project manager?

  1. Continue with the plan as approved and use the management reserve for the gap.
  2. Immediately escalate the funding gap to the project sponsor.
  3. Ask the engineering team to work overtime to finish month 6 work in month 5.
  4. Reschedule non-critical activities to move expenditures into a later period.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials