A new project manager at Cinderwell Water is reviewing the project documents. They notice the project is currently over budget, but the business case shows a high return on investment.

What is the most critical question the project manager should ask?

  1. Which process was skipped that allowed the budget to be exceeded?
  2. Is the project still delivering value that justifies the increased cost?
  3. Who approved the original budget that was clearly insufficient? given the information provided
  4. How can the project team work overtime to recover the budget variance?

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials