easy · Project Management Professional Predictive (Plan-Driven)

A Fenwick Grid planner is missing updates because they are 'waiting for the CPI and SPI calculations' from a junior accountant. The project manager knows the planner is capable of these calculations.

What is the most likely cause?

  1. A skill gap in basic project financial mathematics.
  2. A will gap because the planner is being lazy.
  3. An environment gap because the accounting software is locked, after reviewing the current risk register entries.
  4. A clarity gap regarding roles and responsibilities defined in the RACI.

Sign up free to see the explanation and track your rank →