Coveport Logistics is experiencing an SPI of 0.85 and a CPI of 0.90. The project manager decides to move some activities from sequential to parallel to save time.

What is the most likely consequence of this action?

  1. Increased project risk and potential for rework.
  2. Immediate consumption of the management reserve to fund the change.
  3. A guaranteed improvement in both schedule and cost indices.
  4. Directly increased project costs due to resource overtime.