medium · Project Management Professional predictive
Coveport Logistics is experiencing an SPI of 0.85 and a CPI of 0.90. The project manager decides to move some activities from sequential to parallel to save time.
What is the most likely consequence of this action?
- Increased project risk and potential for rework.
- Immediate consumption of the management reserve to fund the change.
- A guaranteed improvement in both schedule and cost indices.
- Directly increased project costs due to resource overtime.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?