Coveport Logistics is experiencing an SPI of 0.85 and a CPI of 0.90. The project manager decides to move some activities from sequential to parallel to save time.

What is the most likely consequence of this action?

  1. Increased project risk and potential for rework.
  2. Immediate consumption of the management reserve to fund the change.
  3. A guaranteed improvement in both schedule and cost indices.
  4. Directly increased project costs due to resource overtime.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials