medium · Project Management Professional predictive
Solstice Labs is building a research center. The project manager learns that a specific material in the design has been linked to negative health effects for installers, although it is still legal to use.
What is the most responsible action for the project manager?
- Tell the installers to wear extra protective gear to mitigate the risk while using the original material.
- Continue using the material since it is legal and changing it would impact the cost baseline.
- Inform the sponsor that the project is no longer ethical and should be stopped.
- Meet with the architect and safety officer to find a safer alternative material and assess the impact.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?