hard · Project Management Professional predictive
A project manager at Fenwick Grid is managing a predictive power-line installation. A stakeholder requests a modification to the pylon design. The project manager has completed the impact analysis and determined the change will cost 50,000 and delay the project by two weeks.
What is the next logical step?
- Inform the stakeholder that the change is too disruptive to the baseline and must be rejected.
- Update the schedule and cost baselines to reflect the two-week delay and 50,000 increase.
- Present the change request and impact analysis to the Change Control Board (CCB) for disposition.
- Issue a purchase order to the pylon manufacturer for the revised design components.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?