medium · Project Management Professional Predictive (Plan-Driven)

Grayling Software is analyzing three path activities. A: σ=0.6, B: σ=0.8, C: σ=0.

What is the path standard deviation?

  1. 0.48
  2. 1.4
  3. 1.0
  4. 2.0

Sign up free to see the explanation and track your rank →