medium · Project Management Professional predictive
Whitlock Software is procuring new servers. The PM discovers that the preferred low-cost vendor's hardware has double the 'embodied carbon' of a slightly more expensive competitor. The project charter has a specific 'ESG compliance' clause but the procurement budget is tight.
What is the PM's first responsibility?
- Select the high-carbon, low-cost vendor to stay within the tight project budget.
- Inform the vendor that they must reduce their embodied carbon by 50% to be considered.
- Consult the organization's sustainability policy to determine the specific definition and threshold for 'ESG compliance.'
- Reject the high-carbon vendor because their product violates the spirit of the charter clause, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?