KomFi. Academy

hard · Project Management Professional Predictive (Plan-Driven)

Fenwick Grid has a project with AT = 15, ES = 13, and a planned duration of 20.

What is the predicted total project duration (IEAC(t))?

  1. 20.0 months, as per the original baseline.
  2. 23.08 months.
  3. 17.33 months.
  4. 25.0 months.

Sign up free to see the explanation and track your rank →

More Project Management Professional Predictive (Plan-Driven) practice

All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards