hard · Project Management Professional predictive
Fenwick Grid has a project with AT = 15, ES = 13, and a planned duration of 20.
What is the predicted total project duration (IEAC(t))?
- 20.0 months, as per the original baseline.
- 23.08 months.
- 17.33 months.
- 25.0 months.
Sign up free to see the explanation and track your rank →