hard · Project Management Professional predictive

Trestle Ports is managing a logistics project with a predictive schedule. Activity G (5 days) and Activity H (SS+2 with G, 4 days) are on a path with 10 days of total float. The project manager is told to apply resource smoothing.

What is the primary constraint the project manager must respect?

  1. The project completion date and the critical path cannot be changed.
  2. The Start-to-Start lead must be removed to create additional float for smoothing.
  3. All over-allocated resources must be fully resolved regardless of the end date.
  4. The total float of Path G-H must be reduced to zero to ensure efficiency.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials