Trestle Ports is managing a logistics project with a predictive schedule. Activity G (5 days) and Activity H (SS+2 with G, 4 days) are on a path with 10 days of total float. The project manager is told to apply resource smoothing.

What is the primary constraint the project manager must respect?

  1. The project completion date and the critical path cannot be changed.
  2. The Start-to-Start lead must be removed to create additional float for smoothing.
  3. All over-allocated resources must be fully resolved regardless of the end date.
  4. The total float of Path G-H must be reduced to zero to ensure efficiency.