medium · Project Management Professional predictive

Briarpoint Municipal is upgrading its water treatment plant using a predictive life cycle. The project manager is reviewing the schedule and notices that several discretionary dependencies can be adjusted to save time.

What is the primary risk of this specific adjustment?

  1. The risk of rework increases because activities are being performed out of their ideal sequence.
  2. The project will violate mandatory safety codes.
  3. The project will be over budget due to the cost of changing the schedule logic, after reviewing the current risk register entries.
  4. The project team will become demotivated by the lack of clear direction.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials