medium · Project Management Professional predictive
Briarpoint Municipal is upgrading its water treatment plant using a predictive life cycle. The project manager is reviewing the schedule and notices that several discretionary dependencies can be adjusted to save time.
What is the primary risk of this specific adjustment?
- The risk of rework increases because activities are being performed out of their ideal sequence.
- The project will violate mandatory safety codes.
- The project will be over budget due to the cost of changing the schedule logic, after reviewing the current risk register entries.
- The project team will become demotivated by the lack of clear direction.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?