medium · Project Management Professional predictive
Quill Digital is following a predictive schedule. A critical path activity has O=5, M=10, and P=21.
What is the probability that this activity will be completed within 14 days?
- Approximately 16%
- Approximately 84%
- Approximately 97%
- Approximately 50%