Valeport Energy is using a predictive approach for rig maintenance. The lead technician refuses to follow a new environmental ITP, stating it's 'impossible' to do under field conditions.

What is the project manager's best action?

  1. Ask the engineering team to rewrite the ITP to be 'easier' for the field crews.
  2. Warn the lead that the project will be fined if the environmental ITP is not completed.
  3. Provide the lead with a video of a pilot team successfully using the ITP at another site, after reviewing the current risk register entries.
  4. Join the lead in the field for a day to witness the 'impossible' conditions and collaborate on a workable solution.