medium · Project Management Professional predictive
A Harborline Transit project is facing a potential 2-week delay on a non-critical activity that has 3 weeks of total float.
What is the project manager's best course of action?
- Inform the sponsor that the project is now 2 weeks behind schedule, before confirming the relevant stakeholders agree.
- Update the schedule model to reflect the delay and continue to monitor the float.
- Submit a change request to the CCB to extend the schedule baseline.
- Crash the activity to recover the 2 weeks.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?