hard · Project Management Professional predictive
Fenwick Grid is upgrading regional transmission software. A security threat is identified with a probability of 0.15 and a $2,000,000 impact. The risk management plan sets the escalation threshold at $250,000 EMV.
What is the project manager's best course of action?
- Update the risk register with the EMV of $300,000 and escalate to the risk owner in governance.
- Inform the sponsor immediately that the project is over its risk limit.
- Re-allocate $300,000 from the contingency reserve to a third-party security firm to transfer the risk.
- Ask the steering committee to increase the project's risk threshold to $350,000.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?