hard · Project Management Professional Predictive (Plan-Driven)
Dovetail Clinics is facing a resource conflict where a critical analyst has been pulled to a higher-priority portfolio initiative. The project's critical path is now delayed by three weeks.
What is the project manager's best course of action?
- Refuse to release the resource, citing the approved project charter and schedule baseline, before confirming the relevant stakeholders agree.
- Update the schedule to reflect the three-week delay and inform the stakeholders.
- Escalate to the PMO to have the analyst returned to the project immediately.
- Quantify the impact on all project constraints and present a descoping or re-sequencing proposal to the sponsor.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards