hard · Project Management Professional predictive

Dovetail Clinics is facing a resource conflict where a critical analyst has been pulled to a higher-priority portfolio initiative. The project's critical path is now delayed by three weeks.

What is the project manager's best course of action?

  1. Refuse to release the resource, citing the approved project charter and schedule baseline, before confirming the relevant stakeholders agree.
  2. Update the schedule to reflect the three-week delay and inform the stakeholders.
  3. Escalate to the PMO to have the analyst returned to the project immediately.
  4. Quantify the impact on all project constraints and present a descoping or re-sequencing proposal to the sponsor.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials