Citizens of Westfork Municipal are petitioning for a change in the materials used for a new bridge project to improve sustainability.

What is the project manager's first action?

  1. Document the petition as a formal change request and initiate an impact study.
  2. Ask the Mayor's office to respond to the citizens and decide on the materials.
  3. Explain to the citizens that the budget for materials is fixed by the town charter.
  4. Immediately switch to the sustainable material to build community goodwill.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials