A project manager at Solstice Labs is using a 'Tornado Diagram'.

What is the purpose of this tool?

  1. To show the frequency of defects across different categories.
  2. To determine the root cause of a specific quality problem.
  3. To model the project schedule many times to find the probability of finishing on time.
  4. To perform sensitivity analysis and identify which risks have the most potential impact.