medium · Project Management Professional predictive
Quayport Logistics has a BAC of 750,000 for a terminal expansion. The EV is 150,000 and the AC is 200,000. Assuming the variance is systemic, the project manager is asked to report the TCPI required to finish within the original BAC.
What is the result?
- 1.33
- 1.09
- 0.75
- 0.92