Larkspur Health month 6 status shows EV = $110,000 and AC = $135,000. The project manager calculates the To-Complete Performance Index (TCPI) against the original BAC of 1,200,000.
What is the result?
- 0.78
- 0.81
- 1.23
- 1.02