medium · Project Management Professional Predictive (Plan-Driven)

Larkspur Health is developing a predictive diagnostic tool. A regulatory delay threat (probability 0.3, impact -$120,000) and a supply chain risk (probability 0.5, impact -$40,000) are analyzed. An early patent approval opportunity is also noted (probability 0.4, impact +$80,000).

What is the risk-based contingency reserve?

  1. $32,000
  2. $24,000
  3. $160,000
  4. $56,000