At Sable Civic, a project to build a new community center has a Budget at Completion (BAC) of $1,200,000. Currently, the Earned Value (EV) is $400,000 and the Actual Cost (AC) is $450,000. The project manager needs to determine the efficiency required for the remaining work to finish exactly on budget.

What is the TCPI based on the BAC?

  1. 1.07
  2. 0.89
  3. 0.93
  4. 1.13

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials