hard · Project Management Professional Predictive (Plan-Driven)

A predictive project at Harborline Transit is currently at the 14-month mark of a 24-month schedule. The project manager computes the Cost Performance Index (CPI) as 0.82 and the Schedule Performance Index (SPI) as 1.05. The project sponsor is concerned about the budget.

What is the TCPI based on the original Budget at Completion (BAC)?

  1. 0.82
  2. 1.05
  3. 1.22
  4. 0.95

Sign up free to see the explanation and track your rank →