medium · Project Management Professional predictive
A project manager at Whitlock Software is using a To-Complete Performance Index (TCPI) to evaluate the budget. The BAC = $500,000, AC = $200,000, and EV = $150,000.
What is the TCPI to achieve the original BAC?
- 0.86
- 0.75
- 1.17
- 1.33