Nimbus Clinics identifies a threat of data loss (probability 0.01, impact -$1,000,000) and an opportunity for software licensing savings (probability 0.90, impact +$5,000).

What is the total EMV to be reported in the risk report?

  1. -$1,000,000
  2. Escalate the data loss risk to HR.
  3. +$4,500
  4. -$5,500