easy · Project Management Professional predictive
Nimbus Clinics identifies a threat of data loss (probability 0.01, impact -$1,000,000) and an opportunity for software licensing savings (probability 0.90, impact +$5,000).
What is the total EMV to be reported in the risk report?
- -$1,000,000
- Escalate the data loss risk to HR.
- +$4,500
- -$5,500
Sign up free to see the explanation and track your rank →