hard · Project Management Professional predictive
The project manager at Amberline Transit is reviewing the schedule for a light rail extension. Activity A has a duration of 5 days, Activity B has a duration of 8 days, and Activity C has a duration of 4 days. Activity A is a predecessor to both B and C. Activity B and C are predecessors to Activity D, which has a duration of 3 days.
What is the total float for Activity C?
- 0 days
- 12 days
- 4 days
- 8 days
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?