easy · Project Management Professional predictive
Westfork Municipal is installing a new water filtration plant. The project manager conducts a cost-benefit analysis and decides to double the investment in operator training and process documentation (prevention) to avoid future system failures.
What is the underlying principle for this decision?
- Appraisal is more effective than prevention
- Internal failure is preferable to external failure, while documenting the decision in the issue log.
- Gold plating ensures customer satisfaction
- Prevention is generally less expensive than the cost of failure
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?