At Briarpoint Municipal, a predictive infrastructure project is in the Execution phase. The project manager notices that the cost baseline has been exceeded by $50,000 because of an unrecorded scope addition.

What is this phenomenon called?

  1. Gold plating.
  2. Management reserve consumption.
  3. Progressive elaboration.
  4. Scope creep.