hard · Project Management Professional Predictive (Plan-Driven)

A project manager at Coveport Logistics is closing a project. They have confirmed that all deliverables are accepted and the final product has been transitioned.

What must be completed to ensure formal closure?

  1. Inform the sponsor that the project was a success and seek their approval for a team celebration.
  2. Submit a final change request to the CCB to close the cost baseline.
  3. Archive all project records, update the lessons learned register, and release the project team.
  4. Perform a final EVM calculation to prove the project finished under its PTA.