medium · Project Management Professional predictive
At Valeport Energy, a project manager is conducting a performance review of the project team. One engineer is consistently delivering high-quality work but has a conflict of interest because his brother's company is a sub-contractor.
What must the project manager do?
- Require the engineer to disclose the conflict formally and ensure he is not involved in decisions regarding his brother's contract.
- Do nothing, as the engineer's work is high quality and the conflict hasn't caused issues, while documenting the decision in the issue log.
- Remove the engineer from the project immediately to avoid any perception of bias.
- Ask the engineer to convince his brother to lower his prices for the project.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?