A project manager for Trestle Ports is finalizing the WBS. The team disagrees on the level of decomposition for a complex dredging activity.

What should guide the project manager's decision on where to stop decomposing?

  1. Decompose until every task takes no more than 8 hours to complete.
  2. Stop at the third level of the hierarchy to keep the WBS manageable for the sponsor.
  3. Decompose until the work can be reliably estimated and managed as a work package.
  4. Decompose to the smallest possible tasks to ensure maximum control over the team.