hard · Project Management Professional predictive
A project manager for Trestle Ports is finalizing the WBS. The team disagrees on the level of decomposition for a complex dredging activity.
What should guide the project manager's decision on where to stop decomposing?
- Decompose until every task takes no more than 8 hours to complete.
- Stop at the third level of the hierarchy to keep the WBS manageable for the sponsor.
- Decompose until the work can be reliably estimated and managed as a work package.
- Decompose to the smallest possible tasks to ensure maximum control over the team.
Sign up free to see the explanation and track your rank →
More Project Management Professional predictive practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a stakeh… — Which 'Mindset' rule does
- A project manager at Ironvale Grid is leading a session to b… — What is the name of this t
- What is the best action?
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission li… — How should this be represe
- Which process is being performed?