hard · Project Management Professional predictive

A project manager for Trestle Ports is finalizing the WBS. The team disagrees on the level of decomposition for a complex dredging activity.

What should guide the project manager's decision on where to stop decomposing?

  1. Decompose until every task takes no more than 8 hours to complete.
  2. Stop at the third level of the hierarchy to keep the WBS manageable for the sponsor.
  3. Decompose until the work can be reliably estimated and managed as a work package.
  4. Decompose to the smallest possible tasks to ensure maximum control over the team.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials