Larkspur Health is closing a software install. The CPI is 0.98 and the SPI is 1.01. The project manager has $40,000 remaining in the contingency reserve.

What should happen to this money?

  1. Spend the money on additional features to please the customer (gold plating).
  2. Return the unused contingency reserve to the organization's portfolio.
  3. Distribute the remaining funds as bonuses to the project team.
  4. Transfer the funds to a current project that is over budget.