hard · Project Management Professional predictive

Larkspur Health is closing a software install. The CPI is 0.98 and the SPI is 1.01. The project manager has $40,000 remaining in the contingency reserve.

What should happen to this money?

  1. Spend the money on additional features to please the customer (gold plating).
  2. Return the unused contingency reserve to the organization's portfolio.
  3. Distribute the remaining funds as bonuses to the project team.
  4. Transfer the funds to a current project that is over budget.

Sign up free to see the explanation and track your rank →

More Project Management Professional predictive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials