At Westfork Municipal, a union team lead is only following the ITP when the project manager is present. This results in inconsistent water quality data.
What should the PM do?
- Reassign the lead to a less critical part of the plant.
- Require the lead to submit time-stamped photos of each completed ITP step, while documenting the decision in the issue log.
- Install a camera in the testing lab to monitor ITP compliance remotely.
- Meet with the lead privately to discuss the pattern and explore ways to build the lead's ownership of the process.
Sign up free to see the explanation and track your rank →
More Project Management Professional Predictive (Plan-Driven) practice
- What should the project manager do?
- Which logical relationship should be recorded in the schedule model?
- A project manager at Harborline Transit is asked by a… Which 'Mindset' rule does this…
- What is the best action?
- A project manager at Ironvale Grid is leading a session to… What is the name of this…
- What should the project manager have included in the closure documents to address this?
- During the construction of the Ironvale Grid transmission… How should this be represented…
- Which process is being performed?
All Predictive (Plan-Driven) questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards